The team for week 4 from the left are Ron, Mary, Bob, Linda, Jodi, Stel, Suzanne, Susanne, Dan, Gene and Carolyn. |
Mary , Linda, and Suzanne resume cutting soffit and facia and |
and installing it on the north side. |
Susanne, Carolyn and Dan are the ground crew to finish roofing on bedroom 2. |
Bob installing final section of OSB to the wall of bedroom 2. |
Ron finishing installing screws in roofing. |
Dan and Ron install house wrap on bedroom 2. |
Bob and Stel work with homeowner Richard to plan electric for bedroom 2 while |
Carolyn and Susanne install insulation in bedroom 1. |
Ron assists on inside with window installation while Stel and Bob run electric in bedroom 2, |
and Gene and Dan install window from outside, |
and the outside of bedroom 2 is ready for siding. |
Bob and |
Stel finish wiring so inspector can come. |
Ron, Dan, Carolyn and Gene lift first sheet of drywall in bedroom 1. |
The scaffolding has been moved and the siding crew is nearly finished with the east wall |
and they install more soffit and facial |
Dan is especially gifted with "built in scaffolding" to install ceiling drywall |
and Ron assists with the installation. |
The electrical inspector wants 1 more smoke detector so Bob |
and Stel try to find an electrical source for it. |
They finally find a source after enlarging the attic access panel |
and now they have to repair the ceiling around the opening |
and install new trim. |
Since electric & framing passed inspection, Gene begins installing insulation in bedroom 2. |
The east wall is now complete and repainted so we tear down the scaffolding |
and move it to the south wall. |
Suzanne shows off her new toys which are used to hold siding level in place during installation and |
Mary enjoys using the toys. |
Ron and Dan are moving right along with drywall installation. |
Carolyn and Linda painting siding for bedroom 2 |
and Susanne helps too. |
It's been a busy week and Jodi takes a break to dance with homeowner Richard to close out the week. |