As the second week begins, Bub finishes the plumbing in the education building by caulking the fixtures |
and Avis begins reinstalling the refinished cabinet doors. |
Midge and Barb continue sanding doors and cabinets |
and Stel helps Midge by removing hardware. |
Barb applies polyeurothene to the cabinets. |
Denny and Gary patched holes in the drywall in the Thrift Shop |
and applied mud to the seams. |
Cindy and Jack finish rebuilding the porch roof. |
Avis sorted through paint to find usable material to paint the playground equipment. |
Midge paints some missing cabinet doors we found in storage. |
Bub and Steve install 2 used fans in the Thrift Shop. |
Jack and Cindy installed new vinyl base in the Education Building. |
Denny began sanding the swing set |
with the assistance of Gary. |
Avis painted the concrete slab while Cindy and Stel take a break fron the work and |
Gary takes a brief rest. |
Bub tries to make these old light parts into a working fixture for the Thrift Shop and |
his work was successful. |
Stel helps Avis prepare these porch posts for painting and |
Gary begins the painting process. |
Those tree stumps have to go so Stel begins to dig around them and |
Gary lends a hand. |
Stel was able to cut off most of them but this one was a big problem. |
Afterward, Jodi helps to refill the holes. |
Avis replaces damaged floor tile and baseboard in the men's room and |
the ladies room as well. |
The Pastor wanted 2 gates installed on both ends of the choir loft to limit weekday traffic so Steve, Denny and Bub begin the design process. |
and Bub and Steve begin the construction. |
Cindy installs new door stops. |
The first of the refinished doors is dry so Steve, Stel and Avis rehang it while |
Steve and Bub began removing the sanctuary doors for refinishing and |
4 people are needed to carry them so Steve, Bub, Denny and Stel each grab a corner |
and Cindy preps by taping the glass. |
Avis repaints an exterrior door of the Ed. building to make it more "kid friendly". |
Denny and Gary begin repairing @ 200 chairs for the sanctuary by adding screws and wood putty. |
Steve and Bub design security bars for the restroom windows and install them, but |
They were a tad "ugly" so Avis begins covering them with paint |
and Bub reinstalls them. |
The vacuum wasn't working when they cleaned after installing the vinyl base so Cindy and Jack set out to fix it. |
The door locks to the sanctuary were giving everyone trouble so Steve begins to assess the problem while Bub and Stel look on. Eventually, the locks had to be replaced. |
Avis uses a wire brush to clean these cement vehicle stops and |
then she repaints them. |
Avis begins painting the bus toy in the playground while |
Midge works on the bumble bee and duck and |
and Cindy paints the swings |
and Avis continues painting other playground toys. |
Stel and Pastor Augustin meet to discuss project status and additional work to be done. |
Midge is assigned to repaint the speed limit sign |
and it is ready to reinstall |
And the sun goes down on Week #2 |