Dave is sanding and prepping the master bath for painting and Lisa begins painting the walls in the old section |
and the new section. |
Stel repairs a seam in the ceiling of the master bedroom. |
Anne sanding drywall in bedroom 2 closet and |
then applies primer. |
Stel mudding second coat on joints in bathroom and |
then appplies texture to the ceiling. |
Mark is mudding joints in bedroom 2 ceiling with Dave overwatching. |
Mark and Carole begin applying texture to bedroom 2 ceiling and Anne keeps the supply of mud available by mixing and filling paint trays. |
The final look of texture process and |
the final look of Mark after texturing. |
Lisa moves on into the Master bedroom to paint while |
Max and Dave install Luan in preparation for floor coverings. |
Max's first attempt at using leveling compound to smooth out doorway transitions for floor covering and |
he learns how quickly it gets hard. |
Lest we think we will have nothing to do, the coordinators show up with some supplies |
and a whole skid of vinyl click tile for the floors. Something to look forward to. |
Lisa has moved into the living room and dining area to paint |
and then moves into the kitchen |
Max has installed light fixtures and smoke detectors |
and Dave installs outlets. |
Since the siding is complete, we tear down the scaffolding for return to the Disaster Response Center. |
On our final night on week 8, the church threw a pot luck dinner for all the NOMADS and the Volunteer in Missions crew from Colorado. It was a good time of food and fellowship. See you next week. |